Plug-in solar is now legal to use in Great Britain. SI 2026/848 came into force on 27 August 2026 and Ofgem has approved the G98 connection changes — only kits listed on the ENA Type Test Register may be used, and Northern Ireland is not covered. Read the UK legal status

MyPlugInSolar

Policy

Energy Independence Bill and plug-in solar

The Bill introduced to Parliament on 4 November takes enabling powers to make installers register solar PV, batteries, heat pumps and chargepoints with network operators, because fewer than 40% are registered today. Plug-in solar is the one route where registration is already the owner's job.

Written and edited by Christopher Panteli

·

Christopher is the founder and editor of MyPlugInSolar. He oversees the site’s research standards, data tools and editorial process. He is not an electrician or solar installer, and specialist technical claims are sourced from official documentation or reviewed by appropriately qualified professionals.

At a glance

  • The Energy Independence Bill was introduced to Parliament on 4 November 2026 (DESNZ press release and factsheets, same date).
  • The asset visibility measure “provides enabling powers for the Secretary of State to make regulations to require installers of distributed energy assets to register installations with DNOs”. Details come later, in secondary legislation.
  • DESNZ says “less than 40% of these distributed energy assets are currently being registered with DNOs”, and that existing requirements are “unclear and fragmented”.
  • Nothing changes for a plug-in kit now. There is no third-party installer to put an obligation on, the factsheet does not mention plug-in devices, and the owner already notifies the network operator within 28 days under G98.
  • On bills: amendments will scrap gas standing charges, with around 60% of gas account holders expected to save about £45 a year, and the 75% shift of domestic Renewables Obligation costs off bills is put on a legal footing.

The government introduced the Energy Independence Bill to Parliament on 4 November 2026. Most of it is not about plug-in solar, and one measure in it is close enough to be worth reading carefully: a power to require that installed solar PV gets registered with the network operator.

The registration power, in its own words

The asset visibility factsheet describes the measure like this:

The measure creates a clear obligation for installers of distributed energy assets, such as electric vehicle charge points, heat pumps, solar PV and domestic batteries, to register installations with Distribution Network Operators (DNOs).

And on how it will work:

The measure provides enabling powers for the Secretary of State to make regulations to require installers of distributed energy assets to register installations with DNOs, and establish an appropriate monitoring and enforcement regime. Further details on the overall regime will be set out in secondary legislation.

Two words carry the weight: installers and enabling. The obligation lands on whoever fits the equipment, and the Bill does not create it — it creates the power to create it later, by regulations nobody has drafted yet. The factsheet does not mention plug-in solar devices at all, and we are not going to guess whether future regulations will reach them.

Why the government is bothering is the interesting part: It is understood that less than 40% of these distributed energy assets are currently being registered with DNOs, and Existing requirements to register with DNOs are unclear and fragmented, and enforcement regimes are ineffective. DESNZ estimates that if better data let network operators use just one percentage point more of existing low-voltage capacity, it could avoid between £240 million and £571 million of network investment costs by 2050.

Plug-in solar is the awkward case, in a good way

Every asset in that list is normally fitted by a trade: a chargepoint installer, a heating engineer, an MCS solar company. A plug-in kit has no installer. You buy it, you put it up, you plug it in — which is the whole point of the route.

So the obligation as described has nobody to attach to. What already exists instead is a duty on you: notify your network operator through the national portal, within 28 days, under the G98 process. That is not new, it is not optional, and it is the thing people most often skip — see how to register plug-in solar and the G98 notification.

Put the two together and plug-in solar comes out of this looking unusually tidy. The under-40% registration problem the Bill is trying to fix is a problem of installed assets. For plug-in kits the requirement is already explicit, already the owner’s, and already carries a deadline. The gap, if there is one, is how many owners meet it — and no new power is needed to tell you to.

The parts that touch your bill

  • Gas standing charges. The government will bring forward amendments to the Bill to support plans to scrap standing charges on household gas bills, which it says gives around 23 million households more control, with around 60% of gas account holders expected to save an average of £45 a year. This is the Budget measure becoming law — see the Budget and plug-in solar savings. It changes nothing for a kit: solar offsets an electricity unit rate, and the electricity standing charge reform is still only a statement of intent.
  • Renewables Obligation costs. The Bill puts the decision to shift 75% of domestic RO costs from bills to public spending on a lasting legal footing, protecting a saving already in your bill rather than adding one.
  • Charges on re-exported electricity. A separate power lets the Secretary of State remove certain charges from electricity that is re-exported to the grid, including through battery storage or vehicle-to-grid systems, because today these charges are applied unfairly even where the electricity is not actually used and is instead exported back to the grid. That is about batteries and cars, not panels: a plug-in kit exports only what you fail to use at the time, and is paid nothing for it. See whether plug-in solar exports to the grid and the Smart Export Guarantee.

What it means for UK buyers

Nothing to do, and nothing to wait for. No part of this Bill changes what you may buy, install or use today. Enabling powers are not rules.

Do the notification you already owe. If this Bill makes one thing clear, it is that network operators are short of data and the government intends to fix that. Being the household that did not notify is a worse position to be in after this Bill than before it.

Watch the secondary legislation, not the headlines. The scope, the deadlines and the enforcement all land later, in regulations. If those regulations ever mention self-installed devices, that is the moment it matters here, and we will cover it.

Do not read the battery measure as export income. Removing a supplier charge on re-exported electricity is not an export tariff, and a plug-in kit without storage has nothing to re-export. Our calculator still defaults export income to zero, which remains the honest assumption.

Sources

  1. 1. Energy reforms to cut bills and put power back in people's hands — DESNZ (GOV.UK), 4 November 2026
  2. 2. Energy Independence Bill factsheets — Asset visibility installer obligation — DESNZ (GOV.UK), 4 November 2026
  3. 3. Energy Independence Bill factsheets — Removing charges to unlock energy flexibility — DESNZ (GOV.UK), 4 November 2026

Where the UK rules stand

Plug-in solar has been legal to use in Great Britain since 27 August 2026, when SI 2026/848 came into force alongside Ofgem-approved changes to the G98 connection code — provided the kit is listed as compliant on the ENA Type Test Register. Northern Ireland is not covered. See the current legal status and our editorial policy.